Denver Water - Cheesman Dam Upstream Control Project - Phase 1
Cheesman Dam, located at 6,842 feet of elevation, is a primary reservoir for Denver Water who provides the potable water to Denver, CO and surrounding areas. Completed in 1905, it was built by Italian Master Masons using finely set and mortared granite blocks. Cheesman was a technological masterpiece and landmark of civil engineering for decades to come.
The Upstream Control Project, Phase 1, encompasses the replacement of three internal gate valves with new hydraulic valves to be located on the upstream face of the dam. The first step will be to to upgrade the existing bypass outlets. The original bypass outlets, tunneled through the canyon wall for integrity, will be enlarged to accept new stainless steel spool pieces, one weighing 29,000 pounds and two weighing 14,000 pounds each. These spool pieces will be moved just inside the canyon wall and secured in place with anchor bolts, drilled into the native material, and securely grouted to provide a leak free seal. The new stainless steel valves will then be mounted to the spool pieces and protected by trash racks which are to prevent rubble from entering the intake system.
To operate these new valves, a control structure will be built on the crest of the dam. This structure will house the hydraulic pump unit and the controls which will operate the valves. To connect the hydraulic tubing to the valves, holes will be drilled into the dam, exiting into the reservoir next to the gates. One side of the hydraulic tubing will be installed into the holes secured in place with grout, and the other side of the tubing will be connected to the gate.
The diver's work platforms on the reservoir will be "flexi floats", sectional barge units lashed together. These barges will support both a Surface Diving Spread and a complete Saturation System. A staging area will be constructed on the reservoir shore for barge mobilization and support for the duration of the operation.
The initial project tasks will include using an ROV to collect data on the site surveys. This data will be used to design and fabricate custom tooling which will assist in removing the existing valve structure, enlarge the by pass opening, position the new spool pieces, and assist with rock drilling.
Denver Water issues notice of Substantial Completion for all Diving Construction.
"Congratulations on completion of this project milestone. Denver Water recognizes and commends Global Diving & Salvage on a well managed diving construction project with exceptional attention to detail and quality" Jeff Martin Design Project Manager, Denver Water.
Crews will now begin demobilizing the saturation dive system and the dive platform. Twenty two trucks will be utilized to remove Global's gear from the high elevation dam site.
The third and final gate was set in place Friday morning. After being actuated several times on the surface in the presence of Denver Water personnel, the gate was lowered into position and bolted to the previously installed spool. The gate was then operated several more times to ensure proper function. The temporary hydraulic hoses were removed and the permanent piping was installed. The Hydraulic Power Unit was tested, lines purged and the final permanent connection to the gates was made on Sunday. The gate was raised and lowered several more times using the permanent HPU. Final acceptance was granted Sunday afternoon.
Global's saturation system has arrived and been assembled on the surface diving barge. Crews work diligently to ensure all systems are functioning properly with a series of tests and re-checks. The saturation dive crew is on schedule to be pressed in at 0000hrs on July 26, 2010.
Friday at noon, Global's SAT III system began departing Seattle to begin mobilizing at the job site on Tuesday (7/13).
All of the submittals are in, plans approved and the ice finally melting - time to get to work! The barges have been assembled and a shallow water dive station set onboard, Global is beginning work on the Auxiliary Level gate. You can see the spool piece that will be installed inside the existing inlet opening, it will be installed inside the rock opening and anchored in place with 64 anchor bolts. A new hydraulically operated gate valve will be attached to the end of the spool. The entire opening will then be protected with a steel trashrack.
Once the Auxiliary Level Gate has been installed the barge will be brought back to shore, the shallow water dive station will be removed and a Saturation Dive Spread will be installed. The Mid and Low Level Gates will then be installed, similar to that done on the Auxiliary Level.
Project Details
Project News
- 6/20/11: The Cheesman Dam Upstream Control Project (Underwater Magazine)
- 6/13/11: A Major Undertaking - Updating the Outlet Works at Cheesman Dam (QMags)
- 5/1/11: Feature Article: Cheesman (Underwater Magazine )
- 12/1/10: Diver Go Deep For Denver Water Dam Upgrades (American Water Works Association)
- 10/25/10: Divers head under water for Cheesman Reservoir repairs (9 News, Denver)
- 8/16/10: Risky Operation At Cheesman Saves Denver Water $$ (CBS4Denver)
- 7/26/10: Underwater Repairs to Cheesman Dam Start Today (Examiner, Spokane)
- 7/26/10: Divers live underwater during Cheesman Dam overhaul (Fox 31, Denver)
- 7/24/10: Underwater undertaking to fix Cheesman Dam almost underway (Denver Post)
- 3/30/10: Dangerous Diving Task Ahead at Cheesman (CBS 4 Denver)
- 3/29/10: Divers Prepare For Risky Job At Cheesman Dam (CBS 4 Denver)